Securing Future Water Supply for the Communities of West Wallsend and Cameron Park
ESG Alignment
The Cameron Park Reservoir project demonstrates a commitment to reducing environmental impact through sustainable construction practices. The use of horizontal directional drilling for the installation of water mains minimises disruption to the environment, protecting natural habitats and reducing the need for extensive land excavation.
This project supports the well-being of the local community by improving access to a reliable water supply for the residents of West Wallsend and Cameron Park. By investing in long-term water security, the project contributes to public health and enhances the community’s resilience against potential water shortages.
The Cameron Park Reservoir project aligns with best practices in corporate governance by adhering to Hunter Water’s quality and safety standards. Collaboration with Hunter Water highlights a transparent and accountable approach, ensuring stakeholder interests and long-term sustainability goals are prioritised throughout the project.
We’re excited to share the latest updates on our Cameron Park Reservoir project, where our collaboration with Hunter Water is driving enhanced water resources for the community.
What’s Been Happening
We’ve achieved a significant milestone with the installation of the 26-metre diameter roof, which is centrally supported by a single column to meet Hunter Water’s chlorine mixing requirements. The roof and stair tower structures, weighing just under 20 tonnes, were assembled using a 60-tonne crane and electric boom lifts.
Building Strong Foundations
Considerable effort has gone into reaching this stage, including:
- Directional Drilling: Completion of two major directional drills, installing DN 450 and DN 180 HDPE pipes with minimal environmental impact.
- Water Mains Installation: Laying 1280 metres of DN 560 HDPE bidirectional water mains along the access road, integrating critical components such as Scour and Air Valve Tees for a fully operational water network. 50 meters of DN250 HDPE has been installed connecting the Cameron Grove lead in main.
- Concrete Works: Pouring approximately 150 cubic metres of concrete for the reservoir base, engineered for long-term durability.
- Reservoir Walls: Construction of the reservoir walls in 2.4-metre-high segments, culminating in a final 2.5-metre segment, reaching a total height of 7.3 metres. Each segment used around 60 cubic metres of concrete, creating a structure built to last.
Looking Forward
As we move closer to completing the reservoir, pump station, and associated pipework, our focus will shift to finalising stormwater systems, electrical installations, site remediation, and commissioning. It won’t be long before the reservoir goes online, securing future water supply for the communities of West Wallsend and Cameron Park.
Our Commitment
Every step of this project is taken with an eye on sustainability and efficiency. Our construction methods like horizontal directional drilling keep our environmental footprint small, proving that big projects don’t have to mean big impacts.
We’re proud of the progress made so far and look forward to sharing more as we continue to build a better future for Cameron Park.